    Motor replacement on Wednesday: how OPAIRS® recalculates the production plan in a chat

    “We have to replace a motor. When will we run into trouble?” Every production site asks this question sooner or later, and it is usually answered with Excel and gut feeling. In the OPAIRS Showroom the chat answers it in seconds: it re-plans the entire paint line according to several strategies, calculates due dates, raw parts, set-up times and the demand of the following days, and files the best scenario as a proposal. The dashboard shows every scenario next to the current plan immediately.

    OPAIRS dashboard “Paint planning – scenarios” with scenario comparison, on the right the OPAIRview chat widget with the question about a motor replacement and the answer “Critical from Thu 03.12. 06:00”
    Recording from the OPAIRS Showroom: question in the chat, answer with point in time and affected parts, scenario comparison in the dashboard (synthetic test data, German user interface).

    A production plan is good until something happens: a customer calls off more, a raw part is missing, or a motor on the line has to be replaced. That is when the real work starts. The planner copies the plan, re-sorts, recalculates and tries to estimate what it means for the other customers. We rebuilt this workflow in the OPAIRS Showroom: on the paint line of an automotive supplier, with a 72-hour plan, 65 production blocks, 18 painted parts and three customers. All data is synthetic, the logic is the same as at the customer.

    The starting point: a sequence with many dependencies

    On a paint line, orders run one after another like a string of pearls. Every colour change costs set-up time, every block needs the matching raw parts from injection moulding, and customers call off daily via EDI. On top of that come line rules such as the maximum number of skids per block. Whoever changes the plan shifts everything that follows. That is why variants are hardly ever compared in practice: there is one plan, and yesterday’s plan.

    The demo in five steps

    The following sequence is a real recording from the showroom. The planner works in the dashboard and asks questions in the OPAIRview chat widget on the right, just as he would ask a colleague.

    Dashboard paint planning 72h with KPIs for delays, stock-outs and missing raw parts, on the right a prioritised table of findings in the chat: raw part shortage, delay, rule and colour change
    Situation report in seconds: findings by priority, with block, part and cause.

    1. “What is the most urgent problem in the plan?”

    OPAIRS queries the plan and prioritises the findings: block 5 is missing 80 raw parts because injection moulding only restarts in the evening. A customer’s red tailgate trim is 30.7 hours late. In addition, one rule violation and an unnecessary colour change. Below the answer is the verified database query it is based on.

    Chat answer: critical from Thu 03.12. 06:00, motor replacement Wed 02.12. 06:00 to 14:00, best countermeasure S-0001, table of critical parts with customer and shortfall
    First the point in time, then the affected parts and the best countermeasure.

    2. “We have to replace a motor. When should we expect problems?”

    The answer starts with what matters: it becomes critical on Thursday at 06:00. OPAIRS adds the downtime to the shift calendar, recalculates the sequence and checks for every part whether the stock bridges the downtime. Without countermeasures 17 parts are affected, listed with customer, shortfall and point in time. If information such as the exact duration is missing, OPAIRS makes a transparent assumption and says so.

    At the same time OPAIRS simulates several countermeasures: the plan by due date, by best utilisation and a balanced variant that keeps due dates and groups identical colours. Every variant is calculated with pre-production, i.e. additional blocks before the downtime for the parts whose stock is not sufficient. The current plan stays unchanged.

    3. The next demands: EDI call-offs and forecast

    A 72-hour plan only sees three days. For a downtime, however, what is needed afterwards matters. That is why OPAIRS calculates the demand of the following days from two sources: the customer’s EDI call-offs and a forecast from the shipping history, computed by the OPAIRS Forecast Service. The service selects the best model by backtest and runs locally. In the demo, the forecast shows about 12 % more demand than the customer calls off for two blue parts: 187 pieces in total that the current plan does not cover. More on the forecasting service: https://opairs-systems.com/en/insights/opairs-forecasting-zeitreihenprognose-on-premise

    Scenario comparison table with current plan, current plan with downtime and five scenarios: blocks late, delay, delivery reliability, stock-outs, colour changes, set-up time, capacity, forecast demand, pre-production, raw parts, rule violations and plan end
    Scenario comparison in the dashboard: every simulation from the chat appears here without reloading.

    4. “Use the capacity up to the maintenance for pre-production as far as possible.”

    The answer is a scenario comparison with all KPIs. The best scenario may also re-plan the already released orders of the first 24 hours, which in practice is agreed with production, and groups colours consistently. Compared with the current plan including downtime: no block late any more, 100 % delivery reliability, 9 instead of 23 colour changes, 135 instead of 345 minutes of set-up time. The time saved goes into 106 skids of pre-production, and the additional forecast demand is fully covered.

    OPAIRS also says what is not enough: covering all parts would require 146 skids of pre-production, the plan has room for 106. Nine parts remain critical from Thursday instead of seventeen. For the rest, OPAIRS names the options: an extra shift before the downtime or call-offs agreed with the customer. That decision stays with people.

    Chat: re-planning proposal U-0001 with reason and before/after table for delays, stock-outs, raw parts, rule violations, colour changes, utilisation and blocks, below the commands to release or reject
    A proposal, not an automatism: release or rejection with reason by the planner.

    5. “Adopt S-0001”: release by the planner

    One sentence turns the scenario into a re-planning proposal: 41 blocks re-planned, 5 pre-production blocks, before and after for every KPI. The plan only changes when the planner explicitly releases it. This step runs without a language model. On release, OPAIRS logs every change and prepares the transfer to SAP, including new planned orders for pre-production.

    What happens in the background

    • The language model understands the question and selects strategy and parameters. The calculation is not done by the language model but by fixed planning logic in the database: scheduling in the shift calendar, set-up times, raw parts, line rules.
    • Every simulation runs in a transaction that is rolled back afterwards. Only the result is stored as a scenario, the current plan remains untouched.
    • The strategies are transparent: by due date, customer first, best utilisation, balanced with local search, optionally with pre-production and planned downtime.
    • Demand after the plan comes from EDI call-offs and forecast. The model is checked against a baseline by backtest and only used if it performs better.
    • The dashboard reads the scenarios without cache and refreshes automatically. Planners, production management and sales see the same numbers.
    • Releases run deterministically, with a log and a prepared SAP transfer.

    Transferable to other production processes

    The paint line is one example. The same logic of blocks, set-up sequences, due dates, material and capacity fits injection moulding, presses, assembly lines or test benches. At the customer, OPAIRS works with planned orders from SAP, call-offs from EDI and data from MES and warehouse, on-premise in the company’s own network. Strategies and rules are defined together with production planning.

    Live in the showroom

    Would you like to see what your own bottleneck looks like as a scenario? We show the demo live in the OPAIRS Showroom and discuss how it transfers to your production. Write to us: office@opairs-systems.com

    More insights

    Low-poly illustration: the OPAIRS owl on a workstation graphics card, surrounded by circuit lines and a loop arrow – OPAIRS® Runtime 4 with Inkling 2 Mini
    Research & Development

    OPAIRS® Runtime 4: Why OPAIRS Puts Context Fidelity Before Throughput in Industrial AI

    In August the question was: how many tokens per second can we get out of an RTX PRO 4500 Blackwell? Now it is: how many of them are usable? OPAIRS has switched the main model on its development system to Inkling 2 Mini. The new model is somewhat slower at medium load, but it does not invent sources and it marks what it does not know. gpt-oss-20b stays in the stack and does what it does best: highly structured output and fast access to structured knowledge from the data lake on the shop floor.

    Read article
    Diagram: bill of materials with the levels finished product, line, assembly and component, linked via the OPAIRS Knowledge Graph to acceptance report, project plan, assembly instruction, change PDF, drawing, purchase order and supplier e-mail
    Knowledge Management

    Industrial knowledge base with OPAIRS®: From the bill of materials to company knowledge for production, assembly and quotation costing

    A part does not fit, assembly stops, and the worker starts searching: in SAP, in PLM, on the network drive, in the mailbox and among colleagues. OPAIRS organises company knowledge along the bill of materials, attaches drawings, changes and e-mails to the right component and reconciles them with the plan. Instead of searching, people get back to working on the product, and with every project the company’s own knowledge base on processes and production workflows grows.

    Read article